Which DR option is typically deployed with some equipment installed and recovers in hours to days?

Prepare for the Network Operations Management Test with multiple choice questions, each with explanations. Assess your knowledge on protocols, backup strategies, and operational management. Enhance your readiness for the exam!

Multiple Choice

Which DR option is typically deployed with some equipment installed and recovers in hours to days?

Explanation:
In disaster recovery planning, a warm site represents a middle ground where some equipment is already installed and configured, with data and core systems ready to be brought online. This setup allows a restoration of services in hours to days, depending on how much needs to be restored or reconfigured. A cold site would require procuring and installing hardware before services can run, a hot site would be fully prepped and capable of near-instant failover, and a hot spare is a ready-to-go standby component or system. So the description fits a warm site.

In disaster recovery planning, a warm site represents a middle ground where some equipment is already installed and configured, with data and core systems ready to be brought online. This setup allows a restoration of services in hours to days, depending on how much needs to be restored or reconfigured. A cold site would require procuring and installing hardware before services can run, a hot site would be fully prepped and capable of near-instant failover, and a hot spare is a ready-to-go standby component or system. So the description fits a warm site.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy